Brief Project Description:

  • “Complete renovation of City’s historic main corridor designed to address functional, aesthetic, safety, scale and aging infrastructure issues.

Scope:

  • Six Blocks of street with 140’ of rights-of-way.
  • TIGER V Project to complete three blocks with federal/city funds, including the 100 N., 100 S and 200 S. Center Street blocks.

Timeline

Below is a tentative schedule of what to expect over the next three months for the
100 N. Center Street Block:

September

  • Closure of South bound lane intersection of Mulberry/Center Street for installation of new piping (expect closure through September 11)
  • Install new piping down Center Street between Mulberry/Walnut
  • Closure of South bound lane intersection of Walnut/Center Street for installation of new piping
  • Demo sidewalk pavers and right of way bands on 100 N. Center St block

October

  • Install sidewalk pavers and right of way bands on 100 N. Center St block
  • Sidewalk work
  • Pull/terminate/energize new power and electrical service

November

  • Tie-in to new water piping

Below is a tentative schedule of what to expect over the next three months for the
100 S. Center Street Block:

September

  • Street pavement demo
  • Closure of South bound lane intersection of Walnut/Center Street for installation of new piping ` (expect closure through September 26)
  • Install new piping down Center Street between Walnut/Chestnut
  • Closure of South bound lane intersection of Chestnut/Center Street for installation of new piping

October

  • Demo sidewalk pavers and right of way bands on 100 S. Center St block
  • Install sidewalk pavers and right of way bands on 100 S. Center St block
  • Sidewalk work

November – Pull/terminate/energize new power and electrical service

December – Tie-in to new water piping